Budget amount is differe with two different report for the same project and wbs

324 Views

Hi,

I need your valuable input for the below my quires:

The total value of Budget column is differ with below two different report for the same project in production system.

  1. 1.Report 1 :S_ALR_87013558 - Costs -> Budget-Related -> Budget/Actual/Commitment/Rem Plan/Assigned





2- Financials -> Costs -> Budget-Related -> Budget/Actual/Varianc




But if we compere the same two reports with same project code in production copy system (all the business transaction remain same) total amount in

budget column remain same.

is it standard system behavior ? if not how to fix this issue.