S_ALR_87011964_asset balance report_performance issue

26 Views

Hello,

When I run S_ALR_87011964 asset balance report with report date - 12/31 then program gets finished quickly but when I execute for the report date any other date say 03/31 or 04/30 then performance(time to finish) is very bad. Any idea why is that? Is it because of planned depreciation readily available for 12/31 in ANLC and have to be calculated for any other date? Thanks