lead time scheduling with shift

154 Views

Hi expert,

I am facing lead time scheduling with shift.

Can you tell me how to activate lead time scheduling with shift ?

When planned order is created manually by MD11 and scheduled(backward) , I got the result as below.

* start time : 07:20:00

* finish time : 24:00:00

* finish time - start time = 60,000 second

It means system does not take shift into account.

Can you tell me what the missing point is ?

The setting is attached as below.

* scheduling tab in work center

* capacity header in work center

* intervals and shifts in work center

* setup time in routing

60,000 second

* shift definition

* work break schedules

Thank you.