Former Member
Apr 14, 2014 at 05:00 PM

Maintenance Plan: Scheduling period (2)

144 Views


Dear Friends,
Say the scheduling period has been set to 7 years.
Maintenance plans concerned are time-based: monthly. Recent years: all fine. (Plan started 2008).

From this february, there are no called objects, but the future calls have the status "Save to call".
Scheduling itself has ended, because the factory calendar has been set to 2020.

The question: why has the production of call objects been stopped? We expected call objects up to 2020.

SAP cannot extend its scheduling after 2020 because of the calendar, of course. But call objects should be generated up to 2020.

After extending the calendar to 2030, everything looks fine again.

Your explanation and/or link to prper documentation would be very helpful.

Thanks in advance,

Kees Boer (Netherlands)