Hi experts,
I am confusing about lead time scheduling calculation.
Please kindly help me.
I set the data as below.
* In OPU3, choose 6 Backwards in time.
* In OPU5, choose 2 Backwards.
* In routing, Setup time is 1,000 second.
* In work center, Setup formula in scheduling tab is SAP001 (Setup). Other formulas in scheduling are blank.
* Both float before production and float after production are zero.
When I create planned order and scheduling in planned order.
System calculates as below.
Production start time : 16:40:48
Production finish time : 17:00:00
Production finish time - Production start time = 1,152 second
Do you know why there is difference between routing and calculation in planned order ?
Please advise me.