Hi,
We have BOXI3.1 SP3 FP3.1 with Oracle Application Server on Solaris.
We have planned to upgrade to FP6.3 and the path will be SP4 + SP6 + FP6.3.
Also in SP6 OAS is not supported, so we will use weblogic server.
Could you please suggest the sequence of action that I will be following.
Below steps I am thinking not sure if they are correct or is there any short steps.
Stop all services except CMS
Apply SP4
<what actions needed ? Do I need to deploy war files and start BO and keep only CMS up?>
Apply SP6 <Do I need to take any special care here ? CMS database is in Oracle 11gR2>
<Do I need to deploy in weblogic ?><What else I need to take care ?>
Apply FP6.3
Generate war files and deploy
<Any other thing I need to take care>
<Any special consideration for weblogic>
currently the server java is 1.5. Do I need to upgrade the server jav ? If yes then at what stage of upgrade ?
It will be great help if you advise me on this.