Skip to Content
0
Former Member
Apr 09, 2014 at 08:49 PM

GRC AC 10.0 SP14 : Sync job Failed

131 Views

Hi Experts,

We have GRC system with SP14 and target system with GRCPINW (V1000_731) 0005.

While running sync jobs, I get ST22 dump.

Category ABAP Programming Error

Runtime Errors SYNTAX_ERROR

ABAP Program CL_GRAC_AD_UTIL===============CP

Application Component GRC-AC

Date and Time 04/09/2014 18:57:39

Short text

Syntax error in program "CL_GRAC_AD_UTIL===============CP ".

What happened?

Error in the ABAP Application Program

The current ABAP program "GRAC_PFCG_AUTHORIZATION_SYNC" had to be terminated

because it has come across a statement that unfortunately cannot be executed.

The following syntax error occurred in program

"CL_GRAC_AD_UTIL===============CP " in include

"CL_GRAC_AD_UTIL===============CM00P " in

line 219:

"Formal parameter "IV_INCL_FUTURE_DATED_ROLE" does not exist. exist."

" "

" "

" "

The include has been created and last changed by:

Last changed by: "SAP "

Error in the ABAP Application Program

This looks like connection issue to me do checked below things as of now

  1. SM59 connection is working (connection test and authorization tests)
  2. GRC Post implementation document to configure connectors
  3. SPRO config settings (Maintain Connection settings) under Common Component settings -> integration frame work. And along with this, added the connector under Access control -> Maintain Connection settings.
  4. Tables GRACCONNSTAT and GRFNCONNSCNLK are updated in the system
  5. Logical System for the Connector in transaction BD54 (same value as connector)

This looks like connection issue to me.

Any help would be greatly appreciated to resolve this issue