Rescheduling of Maintenance Plans After Changing the Strategy

Dear Experts,

As per the business requirement, we need to change the maintenance strategy hierarchy in order to bring only the higher level package when the miantenance is due ignoring the lower level package.

I have updated the desired hierarchy in the strategy and a list of rescheduling objects are created.

In IP11U, there are couple of options:

  1. Restart in cycle after after last date
  2. Restart in cycle after next date

I want to know what will be the impact on each of this options and what precaution should be taken before going with any of this option., since we have thousands of maintenance plans.

I hope this won't affect the maintenance plans which are not scheduled yet.

If any body can provide the the complete list of activities it will be great.

Thanks a lot!

Cheers,

Raj

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Posted on Apr 09, 2014 at 09:38 AM
    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Apr 28, 2014 at 06:57 AM

    If you have to change the strategy. The system will propose you to reschedule your calls.

    -You could use Restart in cycle after last date option when the next maintenance calls and work will start with reference date equal to the last planned date. Example:

    Last calls: (monthly)

    Planned Date - Call Date

    15.03.14 01.03.14

    15.04.14 02.04.14

    New change (bi-weekly)

    Planned Date - Call Date

    15.03.14 01.03.14

    15.04.14 02.04.14

    30.04.14 23.04.14

    -You could use Restart in cycle after next planned date option when the reference date will be the next planned date.

    Last calls: (monthly)

    Planned Date - Call Date

    15.03.14 01.03.14

    15.04.14 02.04.14

    New change (bi-weekly)

    Planned Date - Call Date

    15.03.14 01.03.14

    15.04.14 02.04.14

    15.05.14 02.04.14

    30.05.14 23.05.14

    Depending on the maintenance team, you should select one option. Also you should test some plans before using IP30.

    Regards,

    Johnny E.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.