on 04-08-2014 12:38 PM
Hello
I'm running multiple product allocation checks for picking capacity, transportation capacity and stock allocation. I run ATP and get a confirmed result.
Then I remove the picking capacity on the confirmed date and re-run ATP so that the order will move to another date in the future with capacity.
If I use delivery group in conjunction with the above the order doesn't move and I get no confirmation but if I remove delivery group the order will confirm.
Any ideas what is going on?
Michael
Hi Michael,
If picking capacity is removed system is performing as expected;
Only a thought, check in delivery group number of deliveries are mandatory.
Thanks,
Bala.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
10 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.