on 04-07-2014 8:08 PM
I have a 3 tier system. Development, QA, Production. I am setting up the TMS. Currently we have it set-up if you release a transport in DEV, it will transfer to all DEV clients and release automatically. It will transfer to the QA clients and release automatically. It will transfer to Production Que and hold.
DEV-->QA-->PROD
Want to change this process so it will hold (not release) in the QA client. How do I set that up?
My confusion is, my understanding is, you create a transport request in development client. When you release the transport it moves thru the transport path to all the clients that are set up in the transport path. I want the transport to auto release in the dev clients, not to auto release in the QA & PROD clients. How do I accomplish this. The SAP documentation read so far does not give me clarity. Thanks
Warren
Hi,
I think what you are looking for is "STMS QA Approval Process"
From the STMS Domain Controller, select the QA System and bring it in change mode.
There in the tab System Attributes, select option "Deliver after confirmation"
Save and distribute the configuration.
This way when you release the TR from DEV, it will move up to the Quality, where you can import in Quality. But it will be holded down there in Quality until unless you approve, after which only it will be delivered to Production.
So to import TRs into Production, you will have to approve them in the system now.
Check Configuring the QA Approval Procedure - Change and Transport System - SAP Library
Also here is a blog-post for the same as well.
Regards,
Akshay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
83 | |
24 | |
12 | |
9 | |
7 | |
6 | |
5 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.