EPM 10NW transport.

Former Member
0 Kudos


What is the sequence of objects to be transported in EPM 10NW.

Like are we supposed to transport something before the model.

Incase of incremental transport in EPM 10NW whatare the steps.

Appreciate inputs..

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Any dependent object should be transported before or atleast in the same request.

For example, models are dependent on dimensions. So, dimensions should be transported first, or you can have the dimensions and the models in the same request.

Hope this helps.

Former Member
0 Kudos

Thanks...is there any documentation that can be referred for the steps to be followed..

damovand
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello,

If you are on BPC10 NW then please check this http://scn.sap.com/blogs/ning/2013/03/27/sap-bpc-10-transport-guide

Best Regards,

Leila Lappin