Hi gurus,

today i have come across a different scenario. while practicing in IDES in a MTO scenario i tried to maintain PIR for a Mterial which have strategy 20.when i try to enter PIR in MD61 it asked for Requirement type I had given LSF. then i RUN MRP it is generated a planned order and IN MD04 i am able to convert the planned order into Production order.

how the system allowed this.

Thanks&Regards,

Venkat.

Accepted Solutions (1)

Accepted Solutions (1)

former_member209265
Active Contributor
0 Kudos

Hi Venkat,

You should not create PIR when the strategy is 20. This is pure make to order. Thats why system was asking the Req type.

Now when you gave LSF, this will allow to create planned order. works like strategy 10 which is MTS.

Check the customizing setting for more info.

Regards,

Krishnendu.

Answers (2)

Answers (2)

former_member184666
Active Contributor
0 Kudos

Hi Venkat,

For any strategy group you can maintain main strategy and secondary strategy. May be the material is having strategy group with main strategy as 20 and secondary strategy as 10. In that case you also maintain PIR for the material and accordingly plan and produce material as MTS.

Check the startegy group config.

Thanks & Regards,

Ramagiri

Former Member
0 Kudos

check if you have maintained strategy group as 20 or only strategy 20.

In case of of group you would be able to maintain alternate requirement type.