Hi All ,
My client requirement is assign Zero budget to project butt in Tcode CJ30 it is not accepting the Zero value . Also they want to Release for same , so I want to know how to assign & release the zero value budget.
Thanks ,
Hi,
As above suggest, for capturing released budget date, you can create a new user status like 'BREL' and when the budget will release, this status will automatically set. And you can easily track out the setting date via JEST and JCDS table.
Also there is a standard Tcode CJ3B, there you can enter the WBS element and find the relevant tranx document like rel or supplement budget with date.
Regards
Shishir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
If you really want to have zero budget, you can budget WSB with 1 USD then release the same amount using CJ32. Again you have to undo all.
-> Edit released amount to zero in CJ32
->return 1usd from same WBS in Cj38.
Then if you run budget report like S_ALR_87013558 you would see zero budget & in Cj33 as zero release.
you can have simple Z program to do all these in single step & set all project to zero.
Recommended to Use this solution as last option..
regards,
Sam
Hi,
Entering zero value, you can not release the Budget.
If your requirement is to capture the date, then better create one more user status as 'Budget Release' and set it. Develop the report based on this status.
Regds,
Channa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Virendra,
please convince your client about the budgeting
budgeting is carried to control the expenses ,zero budgeting concept is not feasible as there shall not be any check over to the orders or requirements.
one thing can be carried out is that ,deactivate AVAC so as to have the budgeting done over to the project with values and the system shall not restrict or check for any value of PR or PO created through the project.
but still i think that you should ask the client and convience him
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
if suppose you want maintain Zero value in CJ30 then what is the meaning of implement PS - without budget control
thanking you
Regards
mahesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mahesh ,
Thanks for reply but we required budget release date for Z report we made z report Sales order Vs budget , and search criteria is budget release date due we not release the budget the project not shows in Zreport , also I need one more help want to know Table for Budget release date or how to get find release date for budget ,
Thanks
HI virendra,
For budget value with zero is not allowed in projects.
And for your second query regarding budget updation report ..you can use CJI8 Report.
Tables for budget update
BPEG Budget revision header
BPEJ Budget revision header
BPGE Overall/annual budget
BPJA Overall/annual budget
Please confirm If it might help you.
Thanks & Regards
Rahul Bansal
User | Count |
---|---|
99 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.