Dear All

When Purchase Requisitions are created from MRP directly, the requsitioner field is filled in with MRP controller Name

But when Planned orders created from MRP are converted to Purchase Requisition by MD15 or through MD04 then requisitioner field is filled in with the user id who does this conversion. Business have a concern here , they would like to have MRP controller name filled in this case also.

Is there any possibility that MRP controller name is filled as Requisitioner when Purchase requisition is created from Planned order also ?

Please let me know your thoughts on this.

Regards

Shyam

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Apr 04, 2014 at 05:29 PM

    its not possible in standard. requisitioner means the person wgo created the PR. in case on MRP run system picks up the responsible mrp ctr, but manual converion of planned order to PR, the person who converts . his name wil come.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.