on 01-19-2017 9:29 AM
Hello Team
We don’t use backward scheduling method to schedule PM orders,
instead we use forwards method. But it seems that the default value backwards scheduling is coming after PM orders are created, we didn’t find any related field in maintenance plan.
Br, Kiran
Hi,
The choice of scheduling type is defined at order level. This is defined in customizing for the order type/plant combination. Customizing transaction is OPU7 or IMG path:
Plant Maintenance and Customer Service > Maintenance and Service Processing > Maintenance and Service Orders > Scheduling > Set Scheduling Parameters
-Paul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks issue get resolved by maintaining the parameter in OPU7.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Kiran,
Some questions:
PeteA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.