Hello,

I'm currently writing my Bachelor's thesis and trying to develop a concept with an PPM (cProjects) integration into SAP Solution Manager.

But I've no experiences with PPM yet. Can you help me out, how to access PPM to create projects that I can later link to my Solution Manager projects (transaction code)?

Thanks a bunch!

Patric Kaufmann

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

5 Answers

  • avatar image
    Former Member
    Apr 04, 2014 at 04:07 AM

    Hi Patric,

    Not sure how much this link can help you.

    Integration of SAP Solution Manager Project and PPM Project - Working with Projects - SAP Library..

    Good Luck for you thesis.

    Regards,

    Runjhun

    Add comment
    10|10000 characters needed characters exceeded

  • Apr 04, 2014 at 04:21 AM
    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 04, 2014 at 07:03 AM

    Hello Patric,

    There is already an integration of PPM to SolMan available since SolMan 7.1 SP10.

    You should talk to the SolMan development team before you go ahead.

    Best, Axel

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 04, 2014 at 07:15 AM

    Thanks to all of you - integration of PPM in SolMan is working now!

    Does anyone of you has experiences with costing projects via cost objects like internal orders (CO) or WBS elements (PS)? I want to transfer the costs of the project (time effort in particular) to SAP ERP...unfortunately, I have no experience with ECC at all, yet. But I think the cost transfer from Solution Manager via PPM to ERP is a pretty neat way to establish fair cost allocation and cost transparency for Change Request Management at the end of the day.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Ravi Ekambaram

      Are there any other prerequisites or configuration tasks to complete?

      I've created a new project in PPM, assigned a SolMan Project. Created a project phase and task in PPM, generated a RfC transaction out of the task and set both project and task in PPM into status "released". tracked time on RfC in SolMan, that is also visible in the project planning section in SolMan. and I still get the same error "does not allow confirmation" when I try to transfer time recording into PPM. I did the configuration in SPRO as you told me: Time Recording for Tasks and Accounting Integration to SAP R/3. is it a prerequisite to have a resource assigned to the project task in PPM?

  • avatar image
    Former Member
    Apr 11, 2014 at 03:51 PM

    Got it done now 😊

    I needed to check the other checkboxes in the confirmation block as well!