on 04-01-2014 11:34 AM
dear expects,
please solve this issue.
Message no. KD503
During settlement, the system puts the sender debits into groups (assignments), which are settled using the same settlement cost element. The settlement assignment is made in the allocation structure, which is stored in the settlement rule for the sender (under settlement parameters).
Cost element 830095 cannot be assigned to a settlement cost assignment in allocation structure A1, and therefore it cannot be assigned to a settlement cost element.
Possible solutions are as follows:
Hi Siva Krishna,
As system guiding you please go to OKO6 and make changes to your allocation structure A1.
Why you are getting this error means, you might have had some postings to the cost element so called 830095, either you have not maintained this to any assignments or you might have not given settlement cost element as it is expecting. The settlement cost element might depend on your settlement receivers, if it is internally done you can use 21 CE category CE to settle, if the settlement is external like (FXA or GL) you need to give 22 CE category CE to settle.
Regards...
Jose
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.