Mar 28, 2014 at 11:32 AM

Load distribution of a Planned Order Operation

91 Views

Hi All,

Need help in understanding an issue here.

For a Planned Order, detailed scheduling happened ,and schedule and Cpacity requirements were generated.

This is the case with just 1 operation. The requirement of this operation is of 1 Hour and schedule was created in Planned Order for the date- 01.07.2014.

But when we go for the capacity evaluation, in CM01 > It shows load devide over two periods > 30.06.2014 and 01.07.2014.

That is,

For, 30.06.2014 load is-->0.614 hrs. Though, Latest start data and time still is same as in Planned order[01.07.2014]

and for 01.07.2014 load is >0.386 hrs. Latest start data and time still is same as in Planned order[01.07.2014] >Which is normal

That is a total of 1 hour.

Please help me understand what made this happen in Capacity evaluation, why we have different data in Planned Order and in CM01.

Why the load got devided over

Regards,

Avinash