Hi All,
Need help in understanding an issue here.
For a Planned Order, detailed scheduling happened ,and schedule and Cpacity requirements were generated.
This is the case with just 1 operation. The requirement of this operation is of 1 Hour and schedule was created in Planned Order for the date- 01.07.2014.
But when we go for the capacity evaluation, in CM01
> It shows load devide over two periods
> 30.06.2014 and 01.07.2014.
That is,
For, 30.06.2014 load is-->0.614 hrs. Though, Latest start data and time still is same as in Planned order[01.07.2014]
and for 01.07.2014 load is
>0.386 hrs. Latest start data and time still is same as in Planned order[01.07.2014]
>Which is normal
That is a total of 1 hour.
Please help me understand what made this happen in Capacity evaluation, why we have different data in Planned Order and in CM01.
Why the load got devided over
Regards,
Avinash