on 03-20-2014 12:04 AM
Hello Experts: My problem is this: PPDS optimizer does not consider the costs of preparation or preparation time in the objective function. Current Scenario: Planning with blocks using configurable features and materials. Matrix preparation created, valued and assigned resources. Objective function evaluated That is working well: Set-up times are observed in the order and working properly. The optimizer runs smoothly. What is not working: The costs and setup times, in the objective function, appear to zero. Thanks for your feedback.
Andrés,
What is the weight distribution for the objective function in your optimization profile? is there a value for the total setup times and setup total costs?
Greetings,
Jorge
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.