Hello Experts: My problem is this: PPDS optimizer does not consider the costs of preparation or preparation time in the objective function. Current Scenario: Planning with blocks using configurable features and materials. Matrix preparation created, valued and assigned resources. Objective function evaluated That is working well: Set-up times are observed in the order and working properly. The optimizer runs smoothly. What is not working: The costs and setup times, in the objective function, appear to zero. Thanks for your feedback.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Andrés,

What is the weight distribution for the objective function in your optimization profile? is there a value for the total setup times and setup total costs?

Greetings,

Jorge