below is the error i am facing when creating  outbound delivery for the sto

Error Log for coll. run 0000000106

47000000019 000010 Shipping for sales org. 1010 dist. chan. 99 from plant 1100 is not possible

47000000019 000010 Delivery from plant 1100 for material M-18 is not possible

Material master is created in both plants and extended to required sales areas and also all the tabs (sales org 1 and 2) are updated with required values.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    Mar 17, 2014 at 02:26 PM

    Srinivas,

    Please check in ME23n for your STO PO whether Shipping tab is coming or not, i think in your case it is not being displayed if so please maintain the below configuration.

    Define shipping data for plants

    SPRO- Material management-Purchasing-Purchase order-set up stock transport order-goto supplying sales area and assign supplying sales area. similarly goto receiving plant and assign the receiving customer which was created in supplying sales area.

    Even after maintain the above config still if you are receiving the same error, please go through the below documents iand compare with your configuration.

    Inter-company STO with SD Delivery, Billing & LIV

    thanks,

    Srinu.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 17, 2014 at 12:10 PM

    Please ensure the customer, vendor and material masters are extended to both sales orgs.

    Thanks,

    Kumar

    Add comment
    10|10000 characters needed characters exceeded

  • Mar 17, 2014 at 01:28 PM

    Hi Mr.Kurma,

    Can you please provide more details?

    1. What about the stock for the material in the relevant storage location?

    2. Have you confirmed if you have assigned the delivery plant (DWERK) to the relevant Sales Area &

        Distribution Channel at SPRO => Assignment => S&D?

    3. Also did you check if you have mentioned the delivery plant (DWERK) in the material master for the material under the Sales Organisation 1 tab?