Planned and Actual costs at the Activity level

Former Member
0 Kudos

Hi all,

Can you tell me if there is a R/3 report which lists out the planned and actual costs for a project and displays it for each network and activity? I want these values at the activity level.

I found a report which lists out these values for each network, but I cannot drilldown to the activity level. Please help.

Thanks,

Satyajit.

Accepted Solutions (0)

Answers (3)

Answers (3)

schneidertho
Advisor
Advisor
0 Kudos

important is that your networks are activity-assigned. otherwise the costs will only show up on network header in PS infosystem.

there is a setting, check either network profile or network type.

Former Member
0 Kudos

Hi,

There is setting in network type. Please go through transaction OPUV i.e.

Change view- Network type paramaeters : overview " Overview.

Uner Network type parameters there is one radio button in front of ActvtyAcctAssgn. Just activate it.

Hope this helps.

Regards

Tushar

Mrinal_K_Roy
Active Contributor
0 Kudos

Budget control at Network activity level

There is a requirement for a customer to activate Budget control functionality at Network activity level..As far as I know , it can be done only at the WBS element level.

Is there any setting or custom development through budget can be controlled at WBS element level.

With regards,

Mrinal K Roy

Former Member
0 Kudos

There are several reports in the system that fill your demands. Try these:

S_ALR_87013532: drill down to network level

S_ALR_87013542: Navigate thru the structure in the left frame. The white sheet symbol represents figures, the yellow folder symbol represents a sum.

Go to the PS Infosystem for furher reports, there is almost nothing you cannot extract from PS