I have problem with CRP, in recipe WC1 is first operation and WC2 is second operation and again WC1 is as third operation (taking highest time cycle). so I run planning, i am using CM25 for capacity leveling, buy in leveling, wc1 is not properly aligned. please give your suggestion,
thank and regards,
vnmvprasad
Hai...
problem solved. set the relationship with +ve value and time given what we allotted in second operation
thank you & regards
vnmvprasad
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Prasad,
Could you please give us more detail on what you mean by "not aligned"? Or could you share the screen shot of your CM25 transaction?
Thanks
Regards,
Julian
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Julian,
Details of Recipe:
Oper phase Work Center Description process time
0010 WC01 Reaction
0020 0010 WC01 Reaction 10 hrs
0030 WC02 layer separation
0040 0030 WC02 layer separation 9 hrs
0050 WC01 Reflection & dist.
0060 0050 WC01 Reflection & dist 18 hrs and so on
Note: Here WC01 is repeatedly used as in third operation (thus WC01= 37 hrs dedicated for this product)
then I run the MRP with MD02 or MD03.after that
In CM25 when i am trying to dispatch the WC01 with starting date as 05.04.2014,
Operation 0010 (WC01) is taking first 10 hours and the next immediately occupies with operation 0060 (WC01) for 18 hr.
So these two operations aligned side by side without leaving any gap for WC02.
please suggest me and thank for your response
Regards
vnmvprasad