Quantity-Based Overhead Rates

Dear Experts,

Quantity-Based Overhead Rates is not calculating in my costing sheet when I do the costing run

but percentage overheads is calculating. is there any separate setting are required for quantity based OH.


I have configured the below settings along with costing sheet


Overhead group in material master and that overhead group is defined in Costing Sheet

unit of measurement for material and the same unit of measurement is configured in Costing Sheet

In cost sheet i have defined OH rate and in OH rate i have given OH key with rate per unit


if there any problem if BOM components Unit of measures are different?

I have searched some other threads also I could not able to find out the reason where I did the mistake


Could you please provide me your inputs


Thanks & Regards

SRI

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • Posted on Mar 15, 2014 at 01:29 AM

    Hi

    If you wanna calculate quantity based ovh on the output material, it won't work. Qty based ovh can work for input components in bom or activity qty in routing

    To calculate quantity based ovh on FG or SFG output material, you should use template allocation instead of costing sheet or add as a workaround add an activity type in routing that represents output qty. Example if your FG plan qty is 10 KG, add activity type in routing with qty as 10 KG and maintain over kg rate in kp26/ kbk6

    Br. Ajay M

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Mar 16, 2014 at 08:12 AM

    Hi

    Everything seems to be OK to me.. If the UoM for which Overhead rate is maintained is different, ensure that UoM Conversion is maintained in the system

    I assume in the BASE, you have included the Cost Element of the Raw Material consumption (GBB-VBR) if you wanna calculate Ovh based on raw material qty

    Similarly, include Sec Cost element of act type if you wanna calculate Ovh based on Activity Qty

    Br, Ajay M

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.