How to revert the plan copy done via CJ9F

Hi Folks,

Here is the scenario:

No budgeting is used in PS ie. no budget profile is assigned to projects.

Initially we are planning cost and revenue for the project and coping these plan value in version "02 : Project Baseline Budget" made for storing data for future reference.

Once the project is released while period end closing plan values are copied to version made for each period but user has performed transaction CJ9F and seleted target version wrong (instead of using Z01 he used 02). thus baseline budget values are overwritten.

Now i want to revert changes in version 02.

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Mar 14, 2014 at 10:36 AM

    Hi...

    if i got it correct the user copied plan cost/rev from version A to version B and now you need to revert to old values of version B.

    As far as i know there is no straight way to do it..but if i could propose a workaround:

    Multiply the plan values of version A with (-1): instead of cost element plan value 100 apply -100, and then copy this to version B. That would bring back the old values of version B.

    Give it a try and let us know

    Best Regards

    Panagiotis

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.