Skip to Content

How to see all changes on Project

Hello,

How I can see all changes done on one Project, including description on project level, budget changed, description and budget on WBS, all networks changes, hours booked, etc. I need date of change and who did that. In CN60 I see something, but I need also budget changes (CJI8) in the same view. It is possible?

Thank you.

Rodica

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Mar 13, 2014 at 08:55 AM

    Hi

    CN60 can be used to monitor project's master data changes. Additional changes to plan or budget values (transactional data) cannot be monitored through CN60 but with relevant plan/budget line item reports..

    Hope it helps

    Panagiotis

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Mar 13, 2014 at 11:19 AM

    Hi,

    Check CN60 for changes in Project Objects & S_ALR_87013560 for budget changes with respective business transaction.

    Regards

    Shishir

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.