on 03-13-2014 8:49 AM
Hello,
How I can see all changes done on one Project, including description on project level, budget changed, description and budget on WBS, all networks changes, hours booked, etc. I need date of change and who did that. In CN60 I see something, but I need also budget changes (CJI8) in the same view. It is possible?
Thank you.
Rodica
Hi
CN60 can be used to monitor project's master data changes. Additional changes to plan or budget values (transactional data) cannot be monitored through CN60 but with relevant plan/budget line item reports..
Hope it helps
Panagiotis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check CN60 for changes in Project Objects & S_ALR_87013560 for budget changes with respective business transaction.
Regards
Shishir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Rodica,
You can also try checking report S_AR_87013558
Once you execute this report, you will see Budget amount shown for specific Project / WBS.
Click on this Budget amount and go to menu Goto-Line items.
You will get to see Display Budget Line items for projects showing text, history of Budget amount datewise.
Check this and see if it helps you.
Regards
Tushar
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.