Dear Expert,
let me simplify the case by an example :
we have set material master as below :
material code : A with price $ 100
material code : B with price $ 120
our purchaser was open a PO # 1234 which is contain material A for 10 PC.
but when our warehouse man check the receiving, the goods for PO # 1234 is material with code B.
(after we communicate with vendor),
they accept our complain but they agree to issue the invoice for PO # 1234 with material A.
my question is :
is it possible in SAP (MIGO-GR) if we do receiving transaction with PO as reference and insert manually for material B?
please advice,
thanks advance and warm regards,
Aang
Hi Aang,
It is not possible until and unless you have item B in that PO. Or you need to create another PO for item B and take the GR 101 against that PO for item B.
You can cancel the document by using MBST if you have allready posted wrongly for item A Or you can reverse the material to vendor.
Regards,
R.Brahmankar