Hi
I'm just testing Defect Correction (we are using ZMTM).
We have Project as a mandatory field (same as standard) and you can ONLY choose projets which have a Change Cycle of TEST. This is no problem and I understand why this is the case.
However, I think I may have found a bug. After you have created the defect, you can click on More > Change Project Assignment. When you do this, you can suddenly choose ANY Project. For example, I just reassigned a defect to a project with a Change Cycle of DEVELOPMENT WITHOUT RELEASE (and it worked).
Is this a bug or is there a reason why you can do this?
Thanks
Shaun
Thanks Dan.
I've actually sorted this out. If you go to /TMWFLOW/VC_PHMD in SM34 you will see what actions are allowed in each phase.
Development without Release had TEST_ASSIGN (which means you can assign existing defects to this phase). Where as Test had TEST_CREATE (create new defecst against this phase).
I have modified it so we can create defects in below phases:
Development without Release
Development with Release
Test
However, I've only allowed transports to be created in Test 😊
Thanks!!
Shaun
Hi Shaun,
This function available for all types of CD's normal change, defect change and urgent change.
And I think, there is no check on release cycle phase, yet.
Also a problem may be a lack of customizing in AIC_SETTINGS for predecessor / successor checks.
Check it, if problem still there, create OSS.
Rg Dan