I am working on quota arangement,in OMEQ i have created 1,2,3.

1 is PO,Schedule line

2 is PO,Schedule ,PR & Planned order

3 is PO,Schedule ,PR,Planned order  & MRP

MD02 i am simulating & seeing the results.

If i assign value either 1 or 2 in in Purchasing view the quota arrangement values the PR is created only for single vendor,but when i assign value 3 in Purchasing view the quota arrangement is working well & the PR is created for 2 different vendors as specified in MEQ1

I want to know why the quota arrangement is not triggered wen value 1 & 2 is assigned & is triggerred when value 3 is assigned.

I have no OPEN PR,PO,Planned order  or stocks in the system when simulating this scenario

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Murugan

On transaction MD02 you are running MRP, therefore, the quota arrangement will only be considered with the option 3 defined on the material master, which also includes MRP.

I wrote the following document about the most frequent issues in this source determination:

MRP: Vendor is not selected and general problems on source determination

BR

Caetano

former_member1186946
Participant
0 Kudos

Thanks

Caetano Almeida

  • SAP Employee

Answers (1)

Answers (1)

sap_pp13
Active Contributor
0 Kudos

Murugan,

   Two types of quota arrangements exist-Allocation quota vs Splitting quota.

Your example of proposals across two vendors are referring to the second piece which works only with MRP with the setting in lot size.

So it should work only with option 3 you have maintained. Option 1 and 2 works for allocation quota.

former_member1186946
Participant
0 Kudos

How to test for allocation quota?What needs to be done for that?

sap_pp13
Active Contributor