ive checked Forum threads and found only few posts about CJI4 and ECP (Easy cost planning).
My question is how can we get detailed plan line items in CJI4 when all data is maintained as ECP in CJ20N transaction.
Here is one screenshots of ECP.
P.S. we do not use any Planning Form.
Best regards
Laurynas Prikockis
11-20-2014 3:25 PM
Hi Laurynas,
We are facing the same problem here. We've tried activating 'integrated planning' flag in version 0 and project profile (OKEV and OPSA). We have activated write plan line items in user status settings (OK02), but still getting no result.
I only get to se plan items for costs planned in CJR2 tcode.
Thanks,
Anna
01-20-2015 11:19 AM
Hey Anna,
i still didnt got any ideas. but only thing you can use CJEO maybe to display values as a report.