No Line Items in CJI4 using ECP

Former Member
0 Kudos

Hello Gurus,

ive checked Forum threads and found only few posts about CJI4 and ECP (Easy cost planning).

My question is how can we get detailed plan line items in CJI4 when all data is maintained as ECP in CJ20N transaction.

Here is one screenshots of ECP.

P.S. we do not use any Planning Form.

Best regards

Laurynas Prikockis

4 REPLIES 4

Former Member
0 Kudos

Hi Laurynas,

We are facing the same problem here. We've tried activating 'integrated planning' flag in version 0 and project profile (OKEV and OPSA). We have activated write plan line items in user status settings (OK02), but still getting no result.

I only get to se plan items for costs planned in CJR2 tcode.

Thanks,

Anna

0 Kudos

Hey Anna,

i still didnt got any ideas. but only thing you can use CJEO maybe to display values as a report.

Greetings

LP

0 Kudos

Thanks Laurynas!!


We'll try with CJEO!!


Regards,

Anna

0 Kudos

Hey Anna,

check my other post regading ECP plan values according to project versioning (simulation)

This should help you out in creating special report with actual and plan values.