Incorrect Amortization calculation - securities zero coupon bonds

Jan 18, 2017 at 10:50 AM

64

avatar image

Dear Gurus,

When we run (TPM1) Amortization Calculation (SAC Gross) is having difference in compared to other client in the same system, Please can someone advice why we are getting difference value.

Amortization cong=fig

5.jpg

TPM12 Report

6.jpg

Amortization log

7.jpg

Thanks,

Prasad

5.jpg (32.8 kB)
6.jpg (72.1 kB)
7.jpg (80.4 kB)
10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

3 Answers

Gustavo Vazquez Jan 18, 2017 at 11:53 AM
0

Hi Prasad,

In TPM13, if you click on Amort Log button, do you get 697.258,59 or 709.325,58 ?

It could be a difference of a day.

Kind Regards

Share
10 |10000 characters needed characters left characters exceeded
prasad raju Jan 18, 2017 at 12:08 PM
0

Hi Gustavo,

In the log its showing 697258.97 but in tpm13 report its showing 709,325.58

TPM 13 amortization log

897.jpg

amortization calculation in spreadsheet as per the system there is no difference in days

78.jpg

TPM13 Main report

435.jpg

not sure why the difference value is coming,how can we find out the difference?


897.jpg (75.2 kB)
435.jpg (65.1 kB)
78.jpg (78.9 kB)
Share
10 |10000 characters needed characters left characters exceeded
Gustavo Vazquez Jan 18, 2017 at 01:45 PM
0

raise OSS message

Share