Hi Guru,

I am a new joiner in implementation team,They wants  implementation of standard functionality on Dead line Monitoring.

Could you please help me to map from QM point of view,with example and steps to configuration required to move further.

Regards,

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Feb 20, 2014 at 12:21 PM
    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 20, 2014 at 12:23 PM

    Hi,

    Please check bellow links, you ll get an idea..

    Inspection type 09 process | SCN

    Add comment
    10|10000 characters needed characters exceeded

  • Feb 20, 2014 at 12:30 PM

    Hi,

    Recurring inspection. This is what it is called & used for deadline monitoring of batches. You would need to activate inspection type 09 and time interval in material master along with other master data for using this functionality.

    There are several thread available with different problem/ scenarios. Since you have not defined any particular issue, so please search and explore.

    Follow this link to understand the basics of Recurring inspection.

    Recurring Inspections for Batch Materials

    This should help you. Go through it and come up with issues you face then.

    All the best !!