Actual cost not reflected in order

former_member224727
Active Participant
0 Kudos

Hi,

We are having one process order in which actuall cost is not reflected in order analysis page, which is causing some variance issue. Could you please help me to figure out reson for it?

Fyi - This is not first order for this material, but seeing issue first time in system for given material order.

Errored order.

Correct order:

Accepted Solutions (1)

Accepted Solutions (1)

SaniketK
Participant
0 Kudos

Hi Eric,

Check activity cost maintained for the activities assigned in work center used for routing in KP26.

Regards,

Saniket

Answers (2)

Answers (2)

former_member184737
Active Contributor
0 Kudos

Hi Eric sun,

        Additionally you have to check the actual booked activity time. Suppose if the activity price is less against your activity based on activity time, system will show with zero value (for example 0.0067). Since, system will consider only two digits value after decimal point. Please check and revert back.

Thanks

former_member184666
Active Contributor
0 Kudos

Hi Eric,

  1. Check for the combination of cost center maintained in workcenter and activity type if any rate is maintained or not in KP26 for the current period.
  2. Check the respective operation if cost relevency indicator is checked or not in production order operation overview.

Thanks & Regards,

Ramagiri