Internal Order (Statistical) Budget check during creation of Purchase Order

Deal All,

I have stuck into the major problem ,kindly help me:

The scenario I am following is:

1.Internal order has been created(Statistical) and it has been released.-KO01

2.Internal order has been budgeted through T code KO22 -Yearly as well as overall.

3.Availability control has been activated.

4.I have created asset with reference to this internal order in the "ORIGIN" Tab Investment order.

5.PO has been created with category "A" and I have entered Asst number in the PO and it has picked the internal order automatically.

6.But when I am posting this PO budget is not getting triggered.Neither at the time of MIGO nor at MIRO also.

I have made all the relevant settings in the configuration but still the budget is not getting hit.

It is hitting budget when I am posting directly through T code -F-90.

Please help me out..

Regards,

Shailesh Bansal

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

3 Answers

  • Posted on Feb 17, 2014 at 06:58 AM

    Hi Sailesh,

    If you want that budget control in CO will be activated also during logistic documents enter (e.g. PO), Commitment management must be activated for Controlling area.

    Kindly do this and see whether it helps you to solve your problem or not.

    regards

    Eugene

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Feb 17, 2014 at 07:19 AM

    Hi..

    You check whether you create statistical cost elements for asset g/l account through the following IMG path: Investment management->Internal Orders as investment measures->planning and budgeting->statistical budget monitoring->statistical cost elements.

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Ajay Maheshwari

      Thanks Ajay for your reply.

      I have maintained object class as investment only and I have maintained the availability control to all type of accounts(++) and 90% i.e warning.

      I have selected Overall budget level for budget check..

      If you require i can share screenshots also with you..

      Regards,

      Shailesh bansal

      8826772100

  • Posted on Feb 17, 2014 at 08:28 AM

    Hi Shailesh,

    Please Check in OME9 whether internal order (CO/PP order) is set to optional for account assignment 'A' category.

    Regards

    Eugene

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Dear Ranu,

      What will happen if i will select that as optional because the PO is taking internal automatically when I am entering the asset.

      Tell me one more thing Do i have to remove the tick of GR NON Valuated in OME9 in Account assignment category A.

      Regards,

      Shailesh Bansal

      8826772100

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.