Scheduling of resources required for projects

Hi,

The scenario is there will be 4 to 5 service projects executed simultaneously. the requirement is to plan for resources
(man and machines) for the service provided.

Eg: a particular skill(P1) is required for 2 projects. how do we schedule the resource across projects. i need to have a dash board or a report showing the resource utilization for a particular project, or time utilization of a resource(in our example time utilization of P1), so that i can plan my project as per availability.

Also the same kind of report needed for equipment.

Can you suggest how to map this requirement in SAP. based on the search I have done in our forum resource utilization(man power) is possible using MRS. please through some light on how to proceed with equipment utilization.

Awaiting your valuable suggestion.

Regards,

Murthy

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

8 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Feb 26, 2014 at 08:02 PM

    Hi,

    Your requirements are met through PPM or MRS. Please go through SAP help portal to get info on MRS and PPM how it works. Certainly you will get an idea. But that kind of standard functionality is not available in PS unless you for Z development as stated by our friend in this thread.

    Not sure what extent the Z development is supplementing HCM functionalities to conclude the sill set and availability to assign resources.

    Regards,

    Sudhakar

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Feb 17, 2014 at 10:52 AM

    Hi, Awaiting your suggestions....

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Feb 24, 2014 at 10:39 PM

    Here we don't use human resource management, but instead we set up different work centers for the resources we want to monitor capacity.

    We assign the work centers to the activities, and then monitor capacity in CM07 (or other CM transaction).


    Hope that helps.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Feb 25, 2014 at 05:21 AM

    Hi Murthy,

    I agree with Timothy..just adding few point here.

    You query sound like a work force planning as you have mentioned that planning of resources.

    If yes,

    You assign activities and work center in it.

    Now maintain HRMS data on work-center.

    These work centers are assigned in activities. and also assign persons on activities in person assignment tab.

    Now , A Person can be assigned in multiple activities in multiple projects.

    you can planned person and check reports based on availability using CMP2 and CMP9.

    It might helps you

    Thanks

    Rahul

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Feb 25, 2014 at 05:28 AM

    Hi Murthy,

    Same scenario I had faced and we went with Z development, where there will be different kinds of skill sets for different projects.

    Resource of each skill set will be planned for different projects. Initially we will plan the resource/machines for the project in Available screen for entire year(according to our requirement).

    Then the actual will be entered for each month in the Actual screen of the particular project.

    The in Z report we can see planned /actual.

    Totally three screens.(Initial availability screen will have skill set options & project details)

    Kindly get back to me if you need more clarifications.

    Regards,

    Sesha

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Feb 28, 2014 at 08:41 AM

    HI Murthy

    If PM is in place and equipments are created then

    please explore the assignment of the PRT from CN22

    here you can assign the particular equipment

    other way work around is standardise activity number as say 1000 for equipment 1 through out system

    and then create a activityin project and schedule.also you can carry out resource allocation

    also you can maintain the equipment number in user field of activity and work with the same.

    other way work around is create work center as equipment and plan it in the activity

    check the report CM01 for work center and it shall show the availability of the workcenter

    for resource planning as already mentioned above it is possible to assign resource and check the availability of resources through transaction CMP2,CMP9, provided HR master data is in place.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Mar 06, 2014 at 09:05 AM

    Murthi,

    It can be sorted out with the help of MRS which allows you plan your resources & your PRT tools avalibility too if need any further help get back pls.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Mar 06, 2014 at 09:32 AM

    hi Murthy ,please mark correct answer ,or please post correct answer so as it shall be helpful to all in future.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.