CN41N report is not matching with the cost plan generated in Project Builder.

Former Member
0 Kudos


As per Project builder, self has created one WBS named WBS A and only one Cost activity called "activity 1". I have assigned 200bucks under the activity so my total budget value for the activity is only 200bucks.

But when i generate in CN41N report, it showing different figure like Activity 1 shows correct figure like 200 bucks but in WBS A shows more than the activity 386 bucks like that.

Can any one help me how to troubleshoot this error.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Execute CJEN and check again.

Regards

Shishir

Former Member
0 Kudos

HI Asarudeen,

This might be because of different currencies. please check the object currency, controlling area currency and transaction currency. And check table TCURR for the currency conversion in this table.

Thanks and regards,

Narender.