Table for dispatch operation hours

In CM25, we can dispatch requirements to work center. I want to know the table for operation dispatch hours. Here is the exact requirement: Say there is requirement of 48 hours and we dispatch it to the a work center PM01 which has a capacity of 8 hrs per day. Now the 48 hours will be dispatched over a period of 6 days. I want to capture the table which captures this split. Thanks!

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    Posted on Feb 13, 2014 at 04:10 PM

    Hi,

    Check KBED,KBKO,KBEZ table

    Thanks

    Girish

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.