Hi,

The latest version of SMART Work Manager for Maximo that I have access to is 7.5.2, packaged with Agentry Server 6.0.22. We have also downloaded and used Agentry server/clients 6.0.38.4 to resolve some bugs.

Will SMART Work Manager for Maximo 7.5.2 run on SMP 3.0, or is there a new version of the work manager for Maximo to be released?

I have seen the road map for SMART Work Manager for SAP, but not the Maximo version, and it is unclear to me whether new versions of the packaged applications for Maximo will be released or if the latest version will work on the latest SMP 3.0 platform.

Any assistance in this area would be greatly appreciated.

Thanks,
Catherine.

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Feb 13, 2014 at 01:36 PM

    1) Yes work manager fro Maximo will run on SMP 3.

    2) No 7.5.2 is the last version

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Feb 13, 2014 at 03:48 PM

    Catherine,

    As Steve mentioned, it will run on SMP 3. However, you will need to make a few tweaks to the java classes to address the new directory structures of SMP 3. The changes have to do with where the server looks for it's configuration files (Agentry.ini and JavaBE.ini) from within the Java classes. I have only done some basic testing with it so far on SMP3 but so far everything is looking good.

    Are you currently a ramp up customer for SMP 3?

    --Bill

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      hi Cathrine,

      Regarding your question about availability of SMP 3.0: Yes, it is true that we are still in the ramp-up phase.

      Once our customer and partners, which are participating in ramp-up, have finalized their projects, SMP 3.0 will become generally available. Since this is project dependent, it's not possible to commit to a specific date. Former Member describes the ramp-up process in his blog, and also explains the 'end of ramp-up'.

      Hope this helps. Cheers,

      Jan

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.