In maintenance plan i am restart the old plan in IP10 what should i given in start of cycle 0 or 100 in count reading. Please need suggestions on this ASAP

mp.png (52.5 kB)
10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Peter Atkin Jan 18, 2017 at 10:25 AM
0

Kumar,

It depends on how you want to align the plan with the current counter reading..

So, assuming the current counter reading is 100, then SAP will determine the next call based on the current counter reading plus the call frequency.

If you use zero, then it will be zero plus the counter frequency.