Hello, All,

We have a co-product A which do not has BOM, it is a consumption parts of FERT B,

When we cost B with CK13N and CK40N,

System report a error no routing or BOM under A.

Is there any problem in that?

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Posted on Feb 12, 2014 at 04:12 AM

    Hi Bryan,

    If you do all relevant setting it will not throw any error.

    An outline of all steps for co-product process:

    1. Create an apportionment structure and assign it in the costing-1 tab of main material.

    2. In BOM, maintain co-product quantity in negative.

    3. Define Source structure with all relevant cost elements.

    4. Switch on "co-product" button in both main and co-product material master either MRP tab or costing-1 tab.

    5. Also, maintain OBYC settings for co-product with GBB-ZOF general modifier.

    6. Run CK11N for co-product values based on apportionment structure assigned in main material.

    Check the below threads where explained on joint production process:

    BR, Srinivas Salpala

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.