PR Release strategy inconsistencies after move from Development(ED1-100) to Testing (ED1-300). It is picking wrong strategy and some do not trigger at all. and Also both CL30N tables has a different total count. please advise, please see attached screenshots

123.png (98.7 kB)
234.png (99.7 kB)
333.png (89.9 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Jan 18, 2017 at 10:28 PM

    The result of transporting different than expected, please review OSS note 86900 – Transport of Release strategies (OMGQ,OMGS)

    Please make sure that you search before asking, I covered this in my blog and there are already > 90 discussions where this OSS note is mentioned.