Dear gurus,
when we receive goods inspection lot is created.now when we put inspection result in inspection result If any critical Material Inspection Characteristic failed then user should not allow to accept the material via usage decision, in this case Usage Decision will always be rejected and anyhow users should not change the Usage decision.
how we configure this scenario
thanks
Use exit
QEVA0010 UD: Usage decision check - While saving UD system will check for results and UD code and then post if the UD is appropriate.
If stock posting check is also required use
QEVA0001 Enhancement: Quantity posting for usage decision