Hello Gurus ,

                    Can we transfer PPDS planned orders to DP thru standard SAP .

Regards,

Nick

Accepted Solutions (0)

Answers (1)

Answers (1)

satish_waghmare3
Active Contributor
0 Kudos

Hello Nick

Please try using Transaction Code :

/SAPAPO/LCOUT - Release to Demand Planning   (Time Series --> To---> Order Series)

Just FYI,   /SAPAPO/LCIN - Opposite way (Order Series --> To---> Time Series)

Also refer this thread :

Time series and Order Livecache Key Figure Copy | SCN

SAP Help for additional details -

Releasing the Supply Network Plan to Demand Planning - Supply Network Planning - SAP Library

Hope this will help.

Thank you

Satish Waghmare

former_member906762
Participant
0 Kudos

Hello Satish ,

                         I know we can release SNP confirmed orders to DP for S&OP purpose using /n/sapapo/snpfcst .

Now in our current design due to time constraint we had to do rough cut capacity planning in PPDS and would like to send constrained PPDS planned orders to DP for S&OP instead of sending all the orders . Is this possible using LCOUT.

Regards,

Nick

satish_waghmare3
Active Contributor
0 Kudos

Hello Nick B,

My input was based on the fact that - Orders in Livecache are maintained as Item Category and organized by Category Group. (  Menu path: SPRO >Advanced Planning and Optimization>Supply Chain Planning>SNP -> Basic Settings>Maintain Category Groups )

Or You can check  the Table: /SAPAPO/APOCGC which shows Category Group and all the Categories it contains.  I think Categories AI AJ, AK is for planned orders which are part of C08 Category Group.

In LCOUT, Within Key figure Assignmet, Select the 999 Key figure copy Option Then Select the Category Group which is mapped to Planned Orders.

Please check if this will help.

Thank you