cancel
Showing results for 
Search instead for 
Did you mean: 

Transportaion lane transportation duration overwritten by PIR PDT

Former Member
0 Kudos


Hi Sap Guru,

The Transportation Duration on the Transportation lane between supplier and 200 plant is being overwritten after changes have been made.  Transportation Duration should represent in-transit time versus total planned delivery time of PO creation to delivery. for example it takes 36 hours for a truck to make delivery, not 15 days per the PDT.

After fix the duration, I set the Transportation lane from 360 hrs to 36 hrs for the same source and destination locations.

kindly suggest me, any setting requre to solve this.

babu

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi Rajendara,

Please refer the OSS note  379006 - Transport duration and planned delivery time in APO and R/3 which has address the same issue.

Regards,

R.Brahmankar