I have a requirement where in i have to calculate the LFI(Load Factor Incentive) from the FQEVENTS no 42, there in i have 3 scenarios.
Scenario 1:
Customer Makes the Payment Promptly
LFI for January Month will be credited to the customer in February Month’s Invoice which will be raised on 1st March.
Scenario 2:
Customer failed to make the payment promptly for the last Month but makes on time for current month
LFI for the month of April will not considered because customer did not make payment on time as well as it should not calculate LFI for the month of May.
Scenario 3:
Customer failed to make the payment promptly.
LFI for should not calculate till at least 2 months Prompt Payment Made.
If my above understanding is correct then we will have to do enhancement for that I need to find out which events are relevant for these scenarios. Please give your scenarios and inputs.
Above are the 3 scenarios based on that i have to calculate the Load Factor Incentive.
Below table is detailed description of the above scenario.
Billing Month | Invoice Date | Due Date | Invoice Amount Inclusive LFI | Payment Date | LFI Amount |
January | 01st Feb | 21st Feb | 10000 | 10th Feb | 100 |
February | 01st March | 21st March | (11000)-100 | 10th March | 110 |
March | 01st April | 21st April | (9000)-110 | 10th April | 90 |
April | 01st May | 21st May | (80000)-90 | 10th May | 80 |
May | 01st June | 21st June | 12000 | 15th June | Nil |
June | 01st July | 21st July | 13000 | 10th July | 130 |
July | 01st Aug | 21st Aug | 14000-130 | 10th Aug | 140 |
Kindly help me find the solution.
02-04-2014 2:13 PM
Event 42 is not the right event. You might use event 20 or R402 where you can post additional documents.
02-05-2014 5:18 AM
Hi Willian,
Hope you are doing well. Thanks a lot for replying.
Can you please let me know the entire scenario so that i can go ahead with this. i need some more clarification on this.
Regards,
Farooq
02-05-2014 7:28 AM
Hi ,
such a development exists for India localization look at path
spro -sap utilities-sap-utilities -india --charges in invoicing -define lpc,prompt payment incentive(PPI)and interest components. May be this will help.
otherwise you will have to look at event R402 (which is called in invoice) and include your custom logic here to post your additional prompt payment doc in next invoicing .