on 02-03-2014 2:19 PM
Hi Friends,
If I have active version management & PO is already released.
I have changed the PO delivery date & PO gone in block.
Can I know if PO release strategy behave differently in case or version management.
Hi,
When you change the PO which is comning from external environmnet , the recheck before save recognizes that this PO comes for release parameters in the system and trigering release for block . Hope so that the version will do nothing for release rather it will track the changes under the version number .
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The release strategy is only reset when there is a value change which lead to a high TOTAL NET VALUE.
Please refer the note: 1961482 - Reset release strategy when version number is set as Characteristic in Customizing
1961585 - Release strategy is not triggered when Version number is set as a Characteristic
If your question is different, please elaborate.
Regards,
AKPT
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hI,
The version management is used for the below purpose .
In this step, you set up the version management facility for external purchasing documents.
For a combination of purchasing organization, document category, and document type, you can:
And please check your release paraments and if there is a change in the release parameters , system will block the PO again asking for a release again .
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.