Skip to Content
0
Former Member
Oct 31, 2005 at 10:06 AM

process chain schedule problem

80 Views

Hi experts

In our product system which is closed development(Scc4). then object changeability settings is following:

Process Chain -- not changeable

Process chain starter -- everything changeable

process variants -- everything changeable

because we don't user put any change in process chain but keep schedule change possibility.

in this case, if I go to re-schedule the process chain, system still said the process chain is not changeable so it's failed.

I only can go to set Process Chain -- changeable everything. then go to change the scedule.

my question is: why I can not change schedule since I have already set process chain starter and process variants as changeable.

another question is: what's different between "everything changeable" and "changeable original"?

thanks in advance