cancel
Showing results for 
Search instead for 
Did you mean: 

Transporting substitution to Production

former_member215688
Participant
0 Kudos

Hello Experts!

Can anybody clarify certain things about a substitution moving to a different envirnoment? As, there was a change made with step 10 and while saving the TR, the three check boxes related to logical rule, transport sets and boolean sets were ticked. What will be the impact, if we tick all three check boxes and what is the appropriate way to move only the step and ticking the boxes accordingly? Issue is, there were some FI postings with different cost centres, which is wrong. The cost centres are picked from the program through maintained SET (GS02). We have compared the history with the after change in production system and it seems everything same. Can anybody throw some light as what could be the reason for the substitution is failing, even if everything seems alright? Is there any way to know, if at all any changes take place anywhere during this whole process of transporting the TR?

Appreciate a quick response!

Thanks in advance!

Regards

Partha 

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member627286
Active Participant
0 Kudos

Dear Partha,

During the transport of a change of validation or substitution one proceeds as follows:

1. Please check with SCMP the tables GB01 or GB01C, whether the in affected systems now are?

2. Transaction GGB4: 'Activate Valid./Subst.' -> application area select -> button of the activation object (here: Change) change define, to set required activation degree save.

3. In the source system from that the transport is supposed to carry out to execute RGUGBR00 as a precaution: Caution, not to set the selection flag 'To generate SubstRout in all Clients' for that anything. The report serves in this case for this purpose for extracting some errors of the changed change (in first syntax error line).

4. No error found? Then it follows on: Transaction GCT0: To choose change, all elements of the Substitution mark: Rules, sets, Boolean Class.

5. Please execute the RGUGBR00 in the target system. Provided that it concerns a system productivity, nothing must be posted when executing this generation report (runs from experience ca. 5 min).

The transport of validation/substitution or changes must always happen for technical reasons in two steps. On the one hand the transport of the validation/substitution or change at themselves by transaction GGB0 or GGB1 must be triggered. A workbench request is created.

This is described in the SAP Note:

1793212 - Transport validation or/and substitution

Best regards,

Vera

Former Member
0 Kudos

Hi Partha Sarathi,

Try to transport

1.Active Substitution definition OKC9

2. Substitution rule

Regards

Anand

former_member215688
Participant
0 Kudos

Hi Anand,

Is it a compulsion to activate the OKC9 everytime, we make any change in the OBBH?

How is OKC9 relevant and linked to it?

Regards

Partha

former_member222241
Active Contributor
0 Kudos

Hi

Yes, you need to activate Substitution each time you make any changes.

The Substitution is activated at two levels viz.

1. Line item level - In this case if you want to have Substitution at document line item level than you activate Callpnt 0001.

2. Document Header - In this case if you want to have Substitution at document header level than you activate Callpnt 0100.

Please note that you have to activate at company code level. In addition to it you can activate any one of the above and not both.

Regards,

Tejas