BCWS and BCWP not calculated

135 Views

Hi PS Experts,

Kindly give solution for following below problem,

When I run CNE1 and then CNSE5 I check that my POC values

are correct, but still, BCWS and BCWP are not calculated

and maintain the value 0.

I’ve created Value category in OPI1 and assigned it to a

secondary cost element (category 61) in OPI2. Then I’ve

assigned cost element to a cost element group.

At the end, I run CNE1 and CNSE5 and BCWS and BCWP

remain with value 0.

How can I fix this?




Thanks & Regards


srikanth ajja.