Authorization Check in CWBQM on planer group

Hi All,

CWBQM allows authorization check with object q_rout. We use a central plant for QM master data and have  different planer groups (plko-vagrp) for the different business lines. Unfortunately q_rout doesn't include planer group.

Is there a way to add an additional authorization check? I couldn't find a suitable BadI or user exit. Any idea?

Thanks!

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Jan 30, 2014 at 10:24 AM

    Hello Bernhard,

    The restriction in CWBQM won't be possible with the help of planner group. You can add authorization object which is there for PM planner group (I_INGRP) but it will be ineffective.

    Kindly refer to SAP note no. 624315 - EWB: MASS authorization check to map your requirement.